The 17-mile long T20 ACR project is expected to start construction in Fall 2028 with a full replacement of 251 deteriorating wood structures with 251 steel structures. Construction is expected to continue from Fall 2028 until Summer 2031 with final restoration efforts lasting until Spring 2032. Public outreach in the communities of Spencer, Charlton, Dudley, and Webster, Massachusetts, has been ongoing. This Project is currently in the pre-construction activity phase and is awaiting permitting approvals.